💰 Cost- ₹ 1035.16 Cr.
💰 Expenditure till date- ₹ 964.25 Cr.
🟢Overall Physical Progress- 75%
🔘Length- 159.81 Km.
🔘Length commissioned- 72.68 km
🔘Remaining- 87.13 Km
🔘Land acquisition completed- 9.40/16.45 Hectare (57.14%)
A) Completed Sections:72.68 km (45.47)
🔘Jalgaon-Pachora
🔘Nandgaon-Manmad
B) Near Completion Sections- 31.79 km (19.89%) (Likely completion this year)
🔘Chalisgaon - Pimperkhed
C) In Progress Sections- 55.35 km (34.63%)
🔘Pachora - Chalisgaon
🔘Nandgaon - Pimperkhed
🟢Completed Works-
☑️Earthwork- 34.10/59.92 Lcum (57%)
☑️Blanketing- 1/7.42 Lcum (13%)
☑️Important Bridges- 1 in Progress (40%)
☑️Major Bridge-11/21 (52%)
☑️Minor Bridge/RUB- 142/295 (48%)
☑️Station Building- 7/15 (47%)
☑️Track linking- 69/160 Track km (43%)
☑️Ballast Supply-2.87/5.02 Lcum
☑️Overhead Equipment OHE Foundations- 774/3168 (24%)
☑️OHE Mast Erections- 513/2443 (21%)
☑️OHE Wiring Track km- 18/160 (11%)
🔴Completion of this new 3rd line will reduce congestion of Mumbai-Howrah busy route and will improve mobility of the trains.
🔘Progress of doubling/3rd/4th lines all over Central Railway’s 5 divisions-
🔘CR has completed 147.77 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3886.95 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2983.47 Crs expenditure done till date.
please wait...Translate to English#Admin #Moderator Source Cr X Handle
Please update this.
#CRInfraUpdates
🔘Manmad- Jalgaon New 3rd line-
💰 Cost- ₹ 1035.16 Cr.
💰 Expenditure till date- ₹ 964.25 Cr.
🟢Overall Physical Progress- 75%
🔘Length- 159.81 Km.
🔘Length commissioned- 72.68 km
🔘Remaining- 87.13 Km
🔘Land acquisition completed- 9.40/16.45 Hectare (57.14%)
A) Completed Sections: 72.68 km (45.47)
🔘Jalgaon-Pachora
🔘Nandgaon-Manmad
B) Near Completion Sections- 31.79 km (19.89%) (Likely completion this year)
🔘Chalisgaon - Pimperkhed
C) In Progress Sections- 55.35 km (34.63%)
🔘Pachora - Chalisgaon
🔘Nandgaon - Pimperkhed
🟢Completed Works-
☑️Earthwork- 34.10/59.92 Lcum (57%)
☑️Blanketing- 1/7.42 Lcum (13%)
☑️Important Bridges- 1 in Progress (40%)
☑️Major Bridge-11/21 (52%)
☑️Minor Bridge/RUB-142/295 (48%)
☑️Station Building- 7/15 (47%)
☑️Track linking- 69/160 Track km (43%)
☑️Ballast Supply-2.87/5.02 Lcum
☑️Overhead Equipment OHE Foundations- 774/3168 (24%)
☑️OHE Mast Erections- 513/2443 (21%)
☑️OHE Wiring Track km- 18/160 (11%)
🔴Completion of this new 3rd line will reduce congestion of Mumbai-Howrah busy route and will improve mobility of the trains.
🔘Progress of doubling/3rd/4th lines all over Central Railway’s 5 divisions-
🔘CR has completed 147.77 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3886.95 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2983.47 Crs expenditure done till date.