#ElectrificationUpdate #30January2020
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 100%
Wiring - 100%
OHE...
more... van - Completed entire section
SSP (2 as on date) - At STP/Sitapur Junction as well as at SD/Sidhauli both SSP's are completed (3rd SSP been spotted - Will update soon).
SP (Only 1) - Basic structure completed and two transformer has been placed at BKT/Bakshi Ka Talab. Approximately 60% work has been completed. (Completion expected by 2020).
Block - Completed and new line has been connecetd with existing line at STP/Sitapur Junction and DAL/DaliGanj Junction as well.
OHE wire energizing - From 10-Dec-2019 wire has been energized.
Trial run : First trial run completed successfully on 14-Jan-2020.
CRS inspection - 05-Feb-2020.
Commercial uses - Any point of time after successful CRS and permission granted by traffic department.