The GNT division is preparing to make NLPD railway station a terminal.
➡️The approved the construction of 2 pitlines in NLPD. Already 1 Pitline construction work in progress. Once the construction of that 1st Pitline is completed after, the construction of the 2nd Pitline will begin.
➡️ The Approval has been given for setting up of water facilities for filling water in coaches.
➡️Construction...
more... of 2 more additional platforms at NLPD will be considered as part of the Guntur-Bibinagar doubling works.Then there will be five platforms in Nallapadu
➡️NLPD station yard is being remodelling.
➡️Pitlines, water facilities and completion of Station yard remodeling after, many trains operating from Guntur will be shifted to Nallapadu for maintenance.
➡️Some of the trains starts from Guntur to BZA side and TEL side are planning to starts from NLPD.