Physical Progress - 75%
🔘Length- 159.81 Km.
🔘Land acquisition completed- 11.39/ 16.45 Hectare (70%)
A)Completed section: 72.68 km (45.47%)
Nandgaon- Manmad
Jalgaon- Pachora
B) Near Completion section: 31.79 km (19.89%)
Chalisgaon- Pimperkhed
C)In Progress section : 55.34 km (34.64%)
Pimperkhed- Nandgaon
Chalisgaon- Pachora
🟢In Progress Works-
☑ Earthwork - 34.10/59.92 Lcum. (57%)
☑ Blanketing- 0.94/7.42 In progress. (13%)
☑ Important bridges– 1 in progress. (40%)
☑ Major Bridge– 11/21. (52%)
☑ Minor Bridge/LHS/RUB- 142/295. (48%)
☑ Station Building- 7/15 (47%)
☑ Track linking – 70/ 160 Tkm (43%)
☑ Ballast Supply- 2.87/ 5.02 Lcum (57%)
☑ Overhead Equipment OHE Foundations -774/3168. (24%)
☑ OHE Mast Erections -513/2443. (21%)
☑ OHE Wiring- 18/160 km (11%)
🔴Completion of this new 3rd line will reduce congestion on busy Mumbai- Howrah route and will improve mobility of the trains.
🔘Progress of doubling/3rd/4th new lines all over Central Railway’s 5 divisions-
🔘CR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date