gyanpur road tak survey kr liya. doubling ka kaam 2 parts mei bata hua hai - first part benares - madho singh (bsb-mbs). sencond part madho singh - allahabd (mbs-ald).
jo bhi work hua hai wo first part yani benares - madho singh ke beech hua hai. foundation ho gya hai. balasting ho chuki hai. agar machine se kaam ho to 2 month me madho singh tak double line ho sakti hai. mannual kaam bhi agar 2-3 shift mei ho to 4 - 5 months me ho sakta hai. lekin dukh ki bat hai ki part 2 yani madho singh se aage koi khas progress nhi dikhi.