Central Railway infra works lead to speeding up of trains-
12 trains now running at 130 kmph on the Igatpuri-Bhusaval-Badnera section
Central Railway has been consistent in its efforts to provide better services...
more... to its passengers. Infrastructure works are being carried out on various sections in order to increase the speed of trains. These include multitracking ( laying of multiple tracks in a section), Over Head Equipment regulation, Signalling works and other technical works.
These works have enabled CR to run trains on these sections at a speed of 130 kmph.
Presently 12 trains are running at the speed of 130 kmph on the Igatpuri-Bhusaval section (308.12 kms) and Bhusaval-Badnera section (218.53 kms)– a total distance of 526.65 kms.
The details are as under
Sr.no
Train no and Name
Section
With effect from
1
12111-CSMT-Amravati Exp
Igatpuri-Bhusaval-Badnera
10.11.2023
2
12112-Amravati-CSMT Exp
Badnera-Bhusaval-Igatpuri
10.11.2023
3
12290-Nagpur-CSMT Exp
Badnera-Bhusaval-Igatpuri
11.11.2023
4
12860-Howrah-CSMT Exp
Badnera-Bhusaval-Igatpuri
11.11.2023
5
12289-CSMT-Nagpur Exp
Igatpuri-Bhusaval-Badnera
12.11.2023
6
12859-CSMT-Howrah Exp
Igatpuri-Bhusaval-Badnera
12.11.2023
7
12106-Gondia-CSMT Exp
Badnera-Bhusaval-Igatpuri
12.11.2023
8
12810-Howrah-CSMT Exp
Badnera-Bhusaval-Igatpuri
12.11.2023
9
12105-CSMT-Gondia Exp
Igatpuri-Bhusaval-Badnera
13.11.2023
10
12809-CSMT-Howrah Exp
Igatpuri-Bhusaval-Badnera
13.11.2023
11
22221-CSMT-Hazrat Nizamuddin Rajdhani Exp
Igatpuri-Bhusaval-
13.11.2023
12
22222- Hazrat Nizamuddin- CSMT Rajdhani Exp
Bhusaval- Igatpuri
14.11.2023
The speed of these trains have been increased after ensuring all safety aspects and technical inspection by the concerned officials. This will decrease running time of trains and improve overall punctuality of train movements.
Earlier Central Railway has enabled running of trains at 130 kmph on the following sections:
Section
Distance
Pune – Daund Section –
75.59 kms
Nagpur-Wardha Section-
78.71 kms
Wardha-Ballarshah Section -
132.34 kms
Nagpur – Itarsi Section -
298.00 kms
Total
584.64 kms
Central Railway presently runs trains at 130 kmph covering a total distance of 1111.29 kms i.e 526.65 kms on the Igatpuri-Badnera section, 75.59 kms on the Pune-Daund section and 509.05 kms on the Itarsi-Nagpur-Wardha-Ballarshah section.
Work to improve speed of trains is in progress on the Daund – Wadi section covering a distance of 337.44 kms and trains are likely to run at 130 kmph on this section.
Central Railway is committed to provide a safe and pleasant journey to its commuters and has been tirelessly working to ensure the same.
please wait...Translate to EnglishYo, listen up! The Central Railway has been doing some major work to speed up their trains. They've been doing all sorts of infrastructure stuff like laying down multiple tracks, regulating the overhead equipment, fixing the signals, and doing other technical work. All of this has allowed them to run trains at a crazy speed of 130 kmph on the Igatpuri-Bhusaval-Badnera section. Right now, they got 12 trains zooming at that speed on that 526.65 km stretch. Here are the details:
1. 12111-CSMT-Amravati Exp - Igatpuri-Bhusaval-Badnera - starting from 10.11.2023
2. 12112-Amravati-CSMT Exp - Badnera-Bhusaval-Igatpuri - starting from 10.11.2023
3. 12290-Nagpur-CSMT Exp - Badnera-Bhusaval-Igatpuri - starting from 11.11.2023
4. 12860-Howrah-CSMT Exp - Badnera-Bhusaval-Igatpuri - starting from 11.11.2023
5. 12289-CSMT-Nagpur Exp - Igatpuri-Bhusaval-Badnera - starting from 12.11.2023
6. 12859-CSMT-Howrah Exp - Igatpuri-Bhusaval-Badnera - starting from 12.11.2023
7. 12106-Gondia-CSMT Exp - Badnera-Bhusaval-Igatpuri - starting from 12.11.2023
8. 12810-Howrah-CSMT Exp - Badnera-Bhusaval-Igatpuri - starting from 12.11.2023
9. 12105-CSMT-Gondia Exp - Igatpuri-Bhusaval-Badnera - starting from 13.11.2023
10. 12809-CSMT-Howrah Exp - Igatpuri-Bhusaval-Badnera - starting from 13.11.2023
11. 22221-CSMT-Hazrat Nizamuddin Rajdhani Exp - Igatpuri-Bhusaval - starting from 13.11.2023
12. 22222- Hazrat Nizamuddin-CSMT Rajdhani Exp - Bhusaval-Igatpuri - starting from 14.11.2023
These trains have been thoroughly checked for safety and all that technical stuff, so you don't gotta worry. This is gonna cut down travel time and make things run smoother. And hey, this ain't the first time they've done something like this. They've already got trains running at 130 kmph on other sections like Pune-Daund, Nagpur-Wardha, Wardha-Ballarshah, and Nagpur-Itarsi. In total, they're covering 584.64 km with those speedy trains. They're also working on the Daund-Wadi section, so you can expect more high-speed action soon. Central Railway is all about making your journey safe and enjoyable, so you know they're doing their best.